Introduction
Efficiently managing resources to complete tasks within specified time frames is a critical skill in project management. This article delves into a real-world problem where determining the number of additional workers needed to complete a job within a given time frame is central. We will use mathematical modeling and logical reasoning to find the solution, ensuring optimal workforce utilization.
Problem Statement
Given the scenario that 6 workers can paint 4 houses in 8 days, how many additional workers are required to paint 8 houses in 4 days?
Step-by-Step Analysis
Step 1: Calculate the Current Work Rate
We start by analyzing the initial condition where 6 workers can paint 4 houses in 8 days. We need to determine the work rate, expressed in worker-days per house.
Formula: Total worker-days Number of workers times; Number of days
Calculation:
Total worker-days needed to paint 4 houses:
Total worker-days 6 workers times; 8 days 48 worker-days
Worker-days per house:
Worker-days per house frac{48 worker-days}{4 houses} 12 worker-days per house
Step 2: Calculate the Total Worker-Days Needed for 8 Houses
Now, we need to find out how many worker-days are required to paint 8 houses, given the previous calculation.
Total worker-days for 8 houses 12 worker-days per house times; 8 houses 96 worker-days
Step 3: Determine the Number of Workers Needed to Finish in 4 Days
Next, we aim to determine the number of workers required to complete the work in 4 days. We set up the following equation to find the number of workers needed:
Workers needed times; 4 days 96 worker-days
Solving for workers needed:
Workers needed frac{96 worker-days}{4 days} 24 workers
Rewritten using proportional reasoning:
Houses ………………… …………………………Workers
4 ……………………… …………………………6
8 ……………………… …………………………x
x 8/4 * 6 12 current workers needed, but we need:
Total: 24 workers - 6 current workers 18 additional workers
Step 4: Conclusion and Solution
In conclusion, to finish painting 8 houses in 4 days, 18 additional workers are needed.
Rewritten Solution:
To calculate the number of workers needed, we can use the original work rate equation:
$frac{4}{6 times 8} frac{8}{w times 4}$
By solving for w (the total workers required), we get:
align'center'>#34;(1/12) (2/w)
#34;w 2 times; 12 24 workers
#34;ANSWER: 18 more workers are needed.
Pertinent Equations and Formulas
Original Work Rate
$frac{4}{6 times 8} frac{8}{w times 4}$
Proportional Reasoning
Houses ………………… …………………………Workers
4 ……………………… …………………………6
8 ……………………… …………………………_
8/4 * 6 12 current workers needed, but 24 total workers - 6 current workers 18 additional workers
Conclusion
The problem of determining the optimal number of workers needed to complete a project within a specified time frame is a practical application of mathematical analysis. By carefully breaking down the problem and using step-by-step logical reasoning, we can determine the exact number of additional workers needed, ensuring efficient use of resources.
The solution shows that 18 additional workers are necessary to complete painting 8 houses in 4 days, leveraging the initial work rate and proportional reasoning.